Mount Green Housing Association Ltd
Overview
Guildmore was employed by our client, Mount Green, to do reinstatement works to a flat and communal area following a fire withing the building. This included Fire Door Replacement and Fire Risk Assessment related works, electrical works, installation of Tunstall Entry and Alarm systems, Fire Systems design and fitting. Our team began this project with investigation works, our aim was to complete the project on time, have good client liaison and have synchronised working with contractors. we faced were delays to materials, tight schedule, dealing with residents trying to visit site, unauthorised access, vehicular movement, contractors coordination and package delimitation. We have learned from this project to ensure our subcontractors look into lead times for materials before the start of project, extend schedules if not doable allowing sufficient time for a relaxed job completion. Engage in better communication with residents and client re site visits and vehicular movement, run pre-start meetings with all contractors and discuss packages well in advance.
Client:
Mount Green Housing Association Ltd
Project Name:
Greylees
Consultant:
Dovetail Building Consultants Ltd
Location:
Filmer Grove, Godalming, Surrey
GU7 3LT
Duration:
4 months (completed July 2022)
Project Value:
£300k
Specifications:
- Strip out flat 5 to a concrete shell
- Design and propose new flat layout
- Design and propose new Kitchen and
Wetroom - Erect new partitions in Timber stud + plaster
board, new electrics and plumbing - Installation of new fire alarms and entry
systems - Installation of new windows, fire doors and
internal doors - Cleaning to a lettable standard upon
completion - The project ran alongside the Fire Doors
and Fire Stopping contract that replaced
all fire doors throughout the building and
made the building fire compliant