Gallions

Client: Gallions Approach Management

Consultant: Hart Dixon
Contract Value: £25 Million
Contract: JCT Design & Build

Scope of work includes for removal of combustible façade elements and installation of new complaint system.

  • Removal of existing insulated(polystyrene) render and installation of new EWI Soltherm render system.
  • Removal of existing terracotta and combustible Kingspan insulation and installation of new Taylor Maxwell terracotta tiles, new sub-grid system,  Siderise cavity barriers and Knauf rainscreen insulation
  • Removal of existing combustible SFS sheathing board and installation of new infill insulation and new Y wall(behind render) and Siniat (behind terracotta) sheathing boards.
  • Removal of existing flammable ACM cladding at roof soffits level and installation of new aluminium cladding panels
  • Removal of existing timber decking and installation of new aluminium decking supplied by Mydek.