Client: Parkgate Aspen
Consultant: Bennington Green
Contract Value: £2.8 Million
Contract: JCT Design & Build
Brief Overview:
The main works included the installation of a new A2-s1,d0 External Wall Insulation System (Mineral Wool Silicone Render) following all combustible materials were removed from the external walls as per the project’s scope. The nature of remediation works is you can never anticipate what you will find, prompting ongoing design details to account for the unexpected.