At Frampton, the roof covers are now complete on all the buildings. On the west block, the brickwork is 95% complete and will complete early in 2020.
On the centre block, the brickwork is 40% complete and on the east block, the brickwork is 30% complete. The 2nd fix dry lining has now been fitted throughout both buildings.
We’re getting ready now for Mechanical and Engineering and the carpentry 1st fix is ongoing. Internally, we’re installing the timber stairs, currently 60% complete