Our development at Ratcliffe Cross Street is taking shape.
At Site A, the tower crane is now in place and the reinforced concrete (RC) frame construction has begun. We are now in the process of pouring the 1st floor slab. At Site B, piling works have finished and the tower crane is in place. The groundworks and drainage works are in progress and we are currently installing the ground beams.
Key facts:
Site A
· Tower Crane in place
· RC Frame Construction has commenced
· Pouring the 1st floor slab.
Site B
· Piling works complete
· Tower Crane in place
· Groundworks and drainage works in progress.
· Installing the ground beams