Works are really picking up the pace at our Ratcliffe Cross Street project on behalf of Notting Hill Genesis.

At Site A, the reinforced concrete (RC) frame has now reached the 5rd floor and the scaffolding is being wrapped around the external face of the new structure.

We will shortly be commencing the metsec frame façade as we follow the frame to the top.

At Site B, the reinforced concrete (RC) frame has now reached the 3rd floor and is climbing to the 4th.

The scaffolding is being wrapped around the external face of Site B.

This development is due to complete in the summer of 2020.

Key updates

Site A

  • RC frame construction in progress
  • 5th floor slab is being poured
  • Currently constructing the columns to take the 6th floor slab
  • Externally the scaffolding works are underway

Site B

  • Groundworks & drainage complete
  • RC frame construction in progress
  • 3rd floor slab has been poured
  • Currently constructing the columns to take the 4th floor slab