Frampton is progressing on time and on schedule
At Frampton, the roof covers are now complete on all the buildings. On the west block, the brickwork is 95% complete and will complete early Read more …
Ratcliffe Cross Street – soon to be called The Kilnworks
At Block A, we’ve painted the walls white and fitted the lights and electrics. The main entry doors have been installed and the pre-plaster work has Read more …
Lyttelton is taking shape for 2020
We’re now laying the brickwork on the 2nd floor and finishing off brickwork up to the 3rd floor. We’re fitting out the flats on the ground Read more …
Moving on fast at 190 Rye Lane in 2020
At Block A, we’ve completed the roof carcass, installed a sprinkler system and fitted the windows. The floors are screeded and outside we’ve cleaned the brickwork. Read more …
Merry Christmas to you all
We hope you enjoy our animated Christmas message in association with CRASH! Charity. Best wishes for a successful 2020. View our animated Christmas card here CRASH Read more …
Lyttelton is bringing new life to Hackney
Client: London Borough of Hackney https://hackney.gov.uk/ EA: Pellings https://www.pellings.co.uk/ 25 homes for Shared Ownership and Social Rent At Lyttelton, Dennis Callan, Project Manager is proud to say Read more …